Report

Works

Weekly Reports have been migrated to our new platform
Go to New Platform
Seminar

June

3월 16, 2025 - 3월 21, 2025

Papers

1. (Hanwha ATS Team) Improving the Scalability and Cost Efficiency of ATS through MOSA Application


2. (ITRC-PI project) A Survey of Physical Internet in Defense Logistics: Prospective and Challenges

70% Progress
Last Week's Progress

1. (Hanwha ATS Team) Improving the Scalability and Cost Efficiency of ATS through MOSA Application
- Requested materials related to the cost efficiency and scalability of ATS through a meeting with Hanwha Team 4 members.
- Target Journal : IEEE Access

2. (ITRC-PI project) A Survey of Physical Internet in Defense Logistics: Prospective and Challenges
- The surveyed content has been organized.

This Week Todo's

1. (Hanwha ATS Team) Improving the Scalability and Cost Efficiency of ATS through MOSA Application
- Chapter 3.2, The Application Cases of MOSA in Hanwha ATS, has been completed and the content has been refined overall.
- Target Journal : IEEE Access

2. (ITRC-PI project) A Survey of Physical Internet in Defense Logistics: Prospective and Challenges
- The surveyed content has been organized.

Project Progress

1. Hanwha team 4 ATS Project

2. Physical Internet Project

60% Progress
Last Week's Project

1. Hanwha team 4 ATS Project
- An SCI paper on the project's achievements is being written.

2. Physical Internet Project
- An SCI paper on the project's achievements is being written.

This Week's Project

1. Hanwha team 4 ATS Project
- An SCI paper on the project's achievements is being written.

2. Physical Internet Project
- An SCI paper on the project's achievements is being written.
- I am writing the section assigned to me in the paper.

Monthly Goals

Complete the Hanwha and PI paper, and submit the JCCI paper.

Annual Goals

Publish three SCI papers.