April 29, 2013 - May 5, 2013

Papers

Title 1:
Monitoring System for Current, Voltage, Phase, Power, and Temperature of Electrical Substation System Over PLC Network (for conference)

50% Progress
Last Week's Progress

Title 1:
Monitoring System for Current, Voltage, Phase, Power, and Temperature of Electrical Substation System Over PLC Network (for conference)
- running the simulation circuit using multisim
- make sure the circuit

This Week Todo's

Title 1: project from Samsung Thales
• Make simulation with multicasting method with 2-20 BESs and 10-100 nodes
• Measure the throughput
• Write the description of the experiment result
Title 2: Monitoring System for Current, Voltage, Phase, Power, and Temperature of Electrical Substation System Over PLC Network

Project Progress

Samsung Thales

80% Progress
Last Week's Project

make the simulation until 48 nodes and 2 BESs
found the throughput

This Week's Project

• Make simulation with multicasting method with 2-20 BESs and 10-100 nodes
• Measure the throughput
• Write the description of the experiment result

Monthly Goals

finish the project and paper for conference

Annual Goals

finish my own paper