Report

Ckwndgur

June 15, 2015 - June 21, 2015

Papers

[1] Proposal for an intelligent lighting system, and verification of control method effectiveness
[2] Lighting Control system including a wireless remote sensor

100% Progress
Last Week's Progress

[1-2]

- Complete the Network-Programing's term project.

This Week Todo's

[1-2]

- Complete the Network-Programing's term project.

Project Progress

Virtualization, MOMAT, Competition(NSLB)

82% Progress
Last Week's Project

[1] Virtualization
- Support for request

[2] MOMAT
- wait the request(Tales's result Report)

[3] Competition
- Prepare the PPT for Satellite Competition

This Week's Project

[1] Virtualization
- Support for request

[2] MOMAT
- wait the request(Tales's result Report)

[3] Competition
- Prepare the PPT for Satellite Competition and mix the new idea with Network-Programing

Monthly Goals

[1] Complete the Project.
[2] Study TOEIC, OPIC

Annual Goals

[1] Complete the Project.
[2] Study TOEIC, OPIC