Report

Brightwill

December 21, 2015 - December 27, 2015

Papers

0% Progress
Last Week's Progress

- did assist work
: 'electronic circuit experiment'
: made questions for final exam
: did exam director work

- worked for IoT project
: modified in DAM_Control app's GUI
: started to write a final report

- worked for virtualization project
: complemented 'hight availability functions and policys' ppt

This Week Todo's

- finish assist work
: score whole report and test paper

- work for IoT project
: add 'wifi communication' function in DAM_Control app
: make codes for android studio

- work for virtualization project
: make virtualization system network with 2 servers and one shared storage

Project Progress

virtualization, IoT(MMS/MQTT)

50% Progress
Last Week's Project

- virtualization
: complemented 'hight availability functions and policys' ppt

- Micro MMS/MQTT
: modified a DAM_Control app's GUI

This Week's Project

- virtualization
: make virtualization system network with 2 servers and one shared storage

- Micro MMS/MQTT
: continue writing a final report
: add 'wifi' function in micro mms-mqtt app

Monthly Goals

1) understand failover functions in VMware and make small virtualization network
2) understand SDN switch code

Annual Goals

1) write the paper about DDS-SDN transmission scheme
: apply for domestic & international journal