Report

Ndh1309

August 5, 2013 - August 9, 2013

Papers

[1] Multiple-Differential Encoding for Multi-Hop Amplify-and-Forward IR-UWB Systems
[2] Maximal Recovery Network Coding Under Topology Constraint

60% Progress
Last Week's Progress

- write and modify for rejected paper of ETFA2013
- write and modify for rejected paper of MILCOM2013
- survey for differential encoding/decoding of coding scheme for modification of milcom2013 submitted paper

This Week Todo's

- write and modify for rejected paper of ETFA2013
- write and modify for rejected paper of MILCOM2013
- prepare NSL seminar

Project Progress

Samsung Thales project for Network virtualization and SDN

50% Progress
Last Week's Project

- survey & study tool of SDN big data
- study for control plane and data plane of Virtual switch system

This Week's Project

- find a menual for simulation tool of big data
- study for control plane and data plane of Virtual switch system

Monthly Goals

- fnish IEEE COMMUNICATIONS LETTERS for LDPC coding scheme.
- fully understand and write the ppt file for Network Virtualization

Annual Goals

- Write down international Conference 2 Paper. [50% complete]
- Write down domestic Conference 2 paper. [0% complete]
- Write down domestic Joural 1 paper