Report

Skyblue70

September 30, 2013 - October 6, 2013

Papers

[1]Enhancing VANET Performance by Joint Adaptation of Transmission Power and Contention Window Size
[2]Contention Window Allocation Scheme for V2V
[2]Contention Window Allocation Scheme for VANETs

85% Progress
Last Week's Progress

-Prepare to submit the ICEIE Letter

-Prepare to present(In ATC Conf.)

This Week Todo's

-Modify several sentence and figure.

-submit the ICEIE Letter

-Prepare to present (In ATC Conf.)

Project Progress

Samsung Thales Project (MDMS)

60% Progress
Last Week's Project

Make a document about program.
Make a debug report.

This Week's Project

Make a document about program.
Make a debug report.

Monthly Goals

Annual Goals

1. y 형 젠더
2. 로봇 청소기
3. 데이터 gathering