Report

Ttungl

February 18, 2013 - February 24, 2013

Papers

Paper1: BEE (rebuild)
Paper2: SEAZOR (cont.)
Paper4: Interference (cont.)

50% Progress
Last Week's Progress

Paper1: BEE (rebuild)-> done.
Paper2: SEAZOR (cont.) coding
Paper4&5: Interference (cont.)
- Reading papers for building the interference modeling in CRNs.

This Week Todo's

Paper2: SEAZOR (cont.) coding
Paper4&5: Interference (cont.)
- Reading papers for building the interference modeling in CRNs.

Project Progress

STP

50% Progress
Last Week's Project

Awaiting for the next work.

This Week's Project

Awaiting for the next work.

Monthly Goals

Paper2: SEAZOR in submission
Paper4&5: Interference for conferences and journals.

Annual Goals