Report

Raihan

May 8, 2023 - May 14, 2023

Papers

5% Progress
Last Week's Progress

1. Resumed survey paper on the approach to the Redundancy issues
2. Broke down the security features of digital wallet for a security-level test approach

This Week Todo's

1. Continue Research about Security Features
2. Preparing for KICS Paper

Project Progress

MANUFACTURING EXECUTION SYSTEM (MES)

5% Progress
Last Week's Project

- Continue studying papers related to MES
- Learn how to test the dataset

This Week's Project

- Continue studying papers related to MES
- Continue learning how to test the dataset

Monthly Goals

1. Preparation for the projects
2. Determining the research area

Annual Goals

1. Continue studying Machine Learning and AI
2. Submit one paper to ICTC-2023
3. Complete at least one Journal Paper